I-24 CHOICE LANES DEAL SET, PUBLIC MEETINGS PLANNED NOV. 17 AND 18

TDOT and its private partner DriveTN have reached a commercial agreement for optional paid lanes on I-24 between I-40 and I-840, with construction expected to finish in 2035, Fox 17 reports. TDOT says the $9.2 billion project should bring the state about $7.7 billion during construction and more than $140 billion over 50 years of operation. Drop-in meetings run 3 to 7 p.m. Nov. 17 at Trevecca Nazarene University and Nov. 18 at the Smyrna Event Center.

Source: Fox 17
Original Story

Questions We Have: How much will drivers pay to use the lanes, and who decides those prices?


Discover more from Not The News

Subscribe to get the latest posts sent to your email.