EAST BANK PROJECTS RACE THE 2030 SUPER BOWL CLOCK

Several East Bank projects will not be finished in time for the 2030 Super Bowl, nash.news reports. The hotel next to the new Titans stadium will pause construction for about two weeks around the game so the site looks as complete as possible for fans and cameras. Construction on TPAC’s new home is set to start in February and wrap up in the third quarter of 2030, though leaders say it will look substantially complete before the game. Work to lower James Robertson Parkway near the Cumberland River bridge is set to start in the second quarter of next year and finish in the third quarter of 2029, and the East Bank Development Authority approved up to $65 million for it.

Source: nash.news, our news partner
Read nash.news

Questions We Have: How will drivers get around downtown while James Robertson Parkway is under construction?